Potato Chip Waste Conveyor

Case Study: Potato Chip Conveyor

 Improving Lead Times with a Custom Fabrication The Challenge A potato chip manufacturer in Tennessee recycles their potato chip waste into an additional revenue stream, however, they were encountering long lead times and high costs to fabricate their potato chip waste conveyor systems. Process Supply was challenged to build and engineer a brand-new conveying system…

Case Study: Salt Drying Heat Exchanger

 Improving Heat Exchanger Lead Time and Life Span The Challange A salt manufacturer in Virginia needed to significantly reduce the 36 week lead time of their heat exchanger fabrication. These heat exchangers are located within the manufacturer’s dryer columns and serve as the primary drying process for their salt. Consisting of eight coils, these heat…